Key points
- Use four priority levels and define each one by the consequence of waiting, not by how important the job feels.
- Combine how critical the equipment is with how bad the problem is right now; any safety risk is critical, whatever the equipment.
- The requester describes what they see; the planner or supervisor sets the priority.
- Check every month how many jobs sit at high and critical, and whether each level meets its response target.
What a priority is for, and why most scales stop working
A priority answers one question: when two jobs compete for the same technician, which one goes first. That is all it is for. It is not a measure of how valuable the equipment is, how senior the person asking is, or when the job is due. Mixing those things into one field is how a priority scale loses its meaning.
The usual way it breaks is quiet. People learn that urgent jobs get done first, so they mark their jobs urgent. Within a few months most of the queue is high or critical, the scale no longer separates anything, and the team goes back to deciding the order by phone calls and whoever walked into the workshop. The fix is not a stricter form; it is clear definitions and one person who applies them.
| Priority | What it means | Example response target |
|---|---|---|
| Critical | A safety or environmental risk, or work has stopped with no workaround. For example: gas smell, oil spill on a walkway, the only packing line stopped. | Start now, other work stops |
| High | Still running but degraded, likely to fail soon, or a backup has been lost. For example: pump vibrating, standby generator failed its test. | Start within 24 hours |
| Medium | Needs doing, no immediate consequence, can be planned. For example: worn guard, sticking door, a light out in a store room. | Planned within a week |
| Low | An improvement or cosmetic job, done when there is a slot. For example: repainting, relabelling, tidying a cable run. | Within a month, or at the next shutdown |
Decide priority from consequence, not from the caller
Two things decide how soon a job must start: how much the equipment matters, and how bad the problem is right now. A small leak on the only chiller in a cold store can outrank a full stop on a machine that has an identical spare beside it. Rank each piece of equipment once as critical, normal or backed up (it has a spare, or little depends on it), so that judgement is not made again on every job. Then read the priority off this table, from how the equipment is doing right now:
| Right now | Critical | Normal | Backed up |
|---|---|---|---|
| Stopped | Critical | High | Medium |
| Degraded | High | Medium | Low |
| No effect yet | Medium | Low | Low |
Safety and environmental risks sit outside the matrix: they are critical whatever the equipment. It often helps to split such a job in two. Making the area safe is critical and happens now; the repair itself can then be rated by the matrix like any other job.
How to set it up, step by step
- Write each level as one sentence in your own site's words, with two real examples from recent jobs. "Critical: someone could get hurt, or work has stopped and cannot continue another way" is clearer than "critical: very urgent".
- Rank your equipment once as critical, normal, or backed up, and keep that on the equipment record, so nobody has to judge it again on every job.
- Decide who sets the priority. The person reporting a fault describes what they see and whether work has stopped. The planner or supervisor sets the priority. The requester's sense of urgency is useful information, not the decision.
- Set a response target for each level that your team can meet on an ordinary week, not on its best week.
- Test it on last month's jobs. Sit down with a supervisor and two technicians and rate twenty recent work orders. Wherever you disagree, the definitions need another sentence.
- Put the definitions where the priority is chosen, on the form or beside the picker, so nobody has to remember them.
The rules that keep priorities honest
Like a code list, a priority scale fails slowly and without complaint. These rules are what keep it working after the first month.
- Critical means drop what you are doing. If a week brings more than a handful of critical jobs, either the site is in real trouble or the word is being misused. Ask for one line of reason on every critical job.
- Requesters describe, planners decide. Ask the requester whether work has stopped and whether anyone is at risk. Those two answers set most priorities on their own.
- Priority is not the due date. A low priority job can still have a fixed date, such as a planned shutdown. Preventive maintenance has its own due dates; raising a service to high just to get it done is a sign the planning is the problem.
- Re-rate when the situation changes, and say why. A temporary fix turns a critical job into a high or medium one. Record the change rather than leaving the old priority in place.
- Review old low jobs instead of escalating them automatically. A low job that has waited three months is a promise that was not kept. Look at the oldest ones every month and either schedule them or close them with a reason. Raising everything that has waited to high only inflates the scale.
- Learn from every critical job. After it is fixed, ask whether an inspection or a preventive task would have caught it earlier. Repeated critical jobs on the same equipment are a case for a root cause analysis.
A worked example: one morning's queue
This is an illustrative example, not a real site. Four requests reach the maintenance supervisor of a food factory before eight in the morning. Each requester calls theirs urgent.
| Request | What the supervisor asks | Priority |
|---|---|---|
| Hydraulic oil on the floor beside a press | Is anyone at risk? Yes, it is a walkway. | Critical to contain and clean now; the leak repair is rated separately |
| Conveyor motor stopped on packing line 1 | Has work stopped? Line 2 can take the load at reduced speed. | High: critical equipment, degraded but with a workaround |
| Standby generator failed its weekly test | Is anything stopped? No, but the site has lost its backup. | High: a lost backup on critical supply |
| Dripping tap in the staff kitchen | Has work stopped? No. | Low |
Two questions sorted four urgent calls into a clear order in a couple of minutes. Without the scale, the job that went first would have been whichever call came in last or loudest, and the oil on the walkway would have waited behind a conveyor that already had a workaround.
Checking every month that the scale still works
Spend a few minutes each month on the work orders closed and still open. You are not judging the work yet; you are checking whether the priorities still separate jobs.
- How much of the queue sits at high and critical. If it is most of it, go back to the definitions with the people who set them.
- Whether each level meets its response target. A level that always misses needs either a realistic target or more hands.
- Critical jobs that turned out to be routine. Talk to whoever raised them, without blame, and add an example to the definition.
- The oldest low jobs. Schedule them, merge them into a planned shutdown, or close them with a reason.
In Solmex every work order carries one of four priorities, low, medium, high and critical, and the work order list puts the most urgent jobs first and can be filtered by priority. The method works the same in any system, including a whiteboard in the workshop.